Capital Works

2019-2020 Program

Capital works programs include the renewal of existing assets, upgrades and construction of new assets required to deliver services to the community.

Council has adopted the 2019-2020 Capital Works Program as below.  Dates are indicative of the planned program, however issues such as poor weather can have a significant impact on the works and adjustments have to be made without notice.

No. Project Approx.
Schedule
of Works
1

​SURFACING WORKS

Alabama Road - Duman Rd to Blackjack Rd

​20 January to 20 March 2020
2 ​Blackjack Road - Rainbow Rd to Towers Hill Turnoff 20 January to 20 March 2020
3 Blackjack Road - Towers Hill Turnoff to Alabama Rd 20 January to 20 March 2020
4 Charlotte Street - King St to Felix St 20 January to 20 March 2020
5 Coane Street - Alabama Rd to End 20 January to 20 March 2020
6 Duman Road  - Alabama Rd to End 20 January to 20 March 2020
7 Gordon Street - Hackett Tce to End 20 January to 20 March 2020
8 Hewett Street  - Prior St to Stubley St 20 January to 20 March 2020
9 Hicks Street - Prior St to Stubley St 20 January to 20 March 2020
10 Hodgkinson Street - Deane St to Church St 20 January to 20 March 2020
11 Hogsflesh Creek Road  - Woodchopper Rd to End of seal 20 January to 20 March 2020
12 Jackson Street - Mosman St to Deane St 20 January to 20 March 2020
13 Lee Street - Mosman St to Deane St 20 January to 20 March 2020
14 Mosman Street - Towers St to Rainbow Rd 20 January to 20 March 2020
15 Old Dalrymple Road - Dalrymple Rd to End of seal 20 January to 20 March 2020
16 Powell Lane - Deane St to Lee St 20 January to 20 March 2020
17 Rutherford Street - Dawn St to Stubley St 20 January to 20 March 2020
18 Stubley Street - Hicks St to Stubley St Landfill 20 January to 20 March 2020
19 Wheelers Road - Dr G Ellis Dr to Acacia Vale Rd 20 January to 20 March 2020
20 Woodchopper Road - Bluff Rd to Pats Rd 20 January to 20 March 2020