| PROJECT |
DESCRIPTION |
TIMELINE |
| York Street Water Main Replacement - Stage 3 |
Water main replacement on York Street between Bluff Road and Natal Downs Road. |
Q1 2025-26 |
| Reseal Program |
Various Roads. |
Completed |
| Myola Road |
Upgrade the first 5km of Myola Road from a 5-6 m wide unsealed road to an 8m wide sealed road. |
Completed |
| Dotswood Road - Stage 2 |
Upgrade of 4.7km of Dotswood Road to provide the final sealed link between existing sealed access and the ADF training facility access point. |
Q4 2025-26 |
| Arterial Road Floodway Upgrades |
Undertake an assessment and detailed design for various arterial road floodway upgrades. |
Q4 2025-26 |
| Scartwater Bridge Replacement |
Undertake an assessment and detailed design for the replacement of the Scartwater Bridge. |
Q4 2025-26 design
|
| Greenvale Scenic Tourism Frame |
The Scenic Tourism Picture Frames Trail project is intended to enhance the tourism experience for visitors, encouraging visitors to explore and promote the region. |
Q4 2025-26 |
| Venus Gold Battery Structural Engineer Assessment |
Structural integrity of the Venus Gold Battery is to be assessed by a qualified/certified engineer to identify works required to maintain. |
Q3 2025-26 |
| Weir Road Reseal |
Resealing of Weir Road from MacPherson Road to Axford Road. |
Completed |
| Bluff Road Reseal |
Resealing Bluff Road from Phillipson Road to Mountain View Road. |
Completed |
| Minor Water Mains & Sewerage Replacements |
Replacements to various asbestos cement water mains & sewerage infrastructure that have reached end of life. |
Q4 2025-26 |
| Mosman Creek Reuse Main Crossing Upgrade |
Replace the current pipeline crossing with new pipework in an under bore. |
Completed |
| New Landfill Shed |
Replace an existing shed damaged beyond repair in a severe storm with a similar structure, redesigned to meet modern standards. |
Q3 2025-26 |
| Charters Towers Sewerage Treatment Plant Biogas Flare Repairs |
Remediation of the Sewage Treatment Plant digestor Biogas Flare and Flame arrestor. |
Q3 2025-26 |
| Ewan Road Rehabilitation - Stage 1 |
Rehabilitation of 3.62km of sealed road and assessment of remaining 10.38km for future rehabilitation or resealing. |
Q2 2025-26 |
| World Theatre Rectification Works |
Rectification works associated with the 2025 storm event to be operationally ready for community use. |
Q4 2025-26 |
| Myola Road Realignment - Stage 1 |
Preliminary investigations, desktop studies, survey, and concept alignment determination to mitigate recurring flood damage caused by Pandanus Creek overflow during the wet season. |
Q4 2025-26 |
| Charters Towers Weir Emergency Intake Protection |
Installation of a protection unit over the suction point of the Weir emergency intake. |
Q3 2025-26 |
| Macrossan Park Tank Stand Renewal |
Install tank on new stand and plumb to existing pipework for the amenities. |
Q3 2025-26 |
| Charters Towers Wastewater Treatment Plant Inflow Metering Upgrade |
Install new flowmeter(s) so that the flow into the wastewater treatment plant can be reliably monitored on SCADA with daily recording of inflow volumes. |
Q4 2025-26 |
| Charters Towers Water Treatment Plant Diesel Pump Intake |
Identify a suitable location, deliver, install and connect the diesel pump into the current delivery mains to allow the delivery of raw water to the WTP in the event of an emergency related to the weir intake and/or weir pumps. |
Q4 2025-26 |
| Sewer Manhole Monitoring Devices |
Identify 5 suitable sites for level monitoring devices, trial devices on site, install equipment and configure on SCADA to alert when sewer gravity man is inundated. |
Q4 2025-26 |
| Dalrymple Saleyards Shade Covers over Sick Bay Pens |
Engineering assessment of existing structure to inform installation of shade covers over sick bay pens. |
Q3 2025-26 |
| Ravenswood Pathway Design - Stage 1 |
Design for the Ravenswood Pathway along Macrossan Street to connect two pubs, public toilet, Post Office and Café. |
Q4 2025-26 |
| Sewerage Treatment Plant Grit Removal Upgrade |
Design and purchase/manufacture a suitable grit removal system that will complement the size and type of plant. |
Q4 2025-26 |
| Charters Towers Weir Tower Safety Upgrade |
Design and install safe and compliant access to these valves for operation and repairs/maintenance. |
Q4 2025-26 |
| Charters Towers Weir Valve Actuation |
Design and install automated valves and all associated equipment to allow remote operation of Weir intake system. |
Q4 2025-26 |
| Day Break Lane Upgrade |
Design and construction of a 730m-long, 7m-wide sealed road. |
Q4 2025-26 |
| Charters Towers Reservoir & Water Main Duplication |
Preparations for the construction of Packages 1 & 2 and the detailed design of Packages 3-7. |
Q4 2025-26 |
| Charters Towers Lynd Highway Cemetery Columbarium Wall Construction |
Construction of a columbarium wall at the Charters Towers Lynd Highway Cemetery. |
Q3 2025-26 |
| Power Backup Solutions for Council Facilities |
Assess current backup capabilities across all Council facilities to inform replacement/upgrade of backup capabilities. |
Q4 2025-26 assessment |
| Charters Towers Visitor Information Centre Wall Renewal |
Addressing the deteriorated cladding and investigating support structures to maintain the overall condition and safety of the building. |
Q4 2025-26 |
| Greenvale Water Treatment Plant Upgrade |
Add flocculant and coagulant chemical dosing and a lamella clarifier to the water supply system that has the potential to successfully treat water during the wet season. |
Q4 2025-26 |
| Saleyards Rear Meeting Room Replacement |
Acquisition of a new prefabricated donga to replace the existing structure. |
Q4 2025-26 |
| Saleyards Splitting of Holding Yards |
14 holding yards, each measuring approximately 12 x 6 meters to be split in half creating a total of 28 pens. |
Q3 2025-26 |