Pavement reconstruction at roundabout - Monday 6 November 2017

Council contractors will be undertaking profiling and placing bitumen treated base (BTB) at the Gill and Boundary Streets roundabout.  These works will commence Monday 6 November 2017 until Wednesday 8 November 2017.  The works will involve night shifts to minimise disruptions, however, lane closures with detours will still be present.  Following these works Council staff will then complete the remaining traffic islands.

Gill Street roundabout update - One lane closure

As works on the Gill and Boundary Streets roundabout progresses, the East bound lane of Gill Street (hospital side) will be closed from Wednesday 13 September 2017 for a period of 2 weeks.  Detours will be in place via Mary Street.  The section of Boundary Street between Gill and Mary Streets will also be closed to traffic (local traffic will have guided access).

Gill Street pavement reconstruction - Vulture Street to Enterprise Road

Council staff will be undertaking profiling and placing bitumen treated base (BTB) on Gill Street between Vulture Street and Enterprise Road.  These works are expected to commence Thursday 21 September.  The works will involve night works to minimise disruptions, motorists are to expect lane closures with detours.

Council acknowledges that the works may cause some inconvenience and appreciates the public's cooperation.

Should you require any further information please contact David Fletcher, Techncial Services Manager on 4761 5300.

Preliminary roundabout works and further reconstruction works commence in Gill Street

Council staff have commenced preliminary roundabout works at the Gill & Boundary Streets intersection.  Preparation for pavement replacement between Vulture & Enterprise Streets has also commenced with the removal of traffic islands.

Gill Street roundabout update August 2017

Council staff will be undertaking works at the Gill & Boundary Streets intersection to construct a roundabout.  These works will take approximately four weeks.  During these works there will be disruptions to traffic.  Detours will be in place via Hodgkinson Street and Mary Street (between Vulture and High Streets).   

These works are planned to commence late August.  In addition to these works, linemarking will also be completed during the month of August on the completed asphalt sections of Gill Street.

For road rules at a roundabout please refer to https://www.qld.gov.au/transport/safety/rules/road/roundabouts.

 

Council acknowledges that the works may cause inconvenience and appreciates the public's cooperation. 

Should you require any further information, please contact David Fletcher, Technical Services Manager on 4761 5300.

 

Gill Street Reconstruction Stage 1 April 2017

Gill Street Pavement Reconstruction 2017/2018

The following works are planned:

  1. Profile and place BTB Boundary Street intersection, construct roundabout, lay asphalt, July 2017
  2. Replace water main Church Street to High Street, August 2017
  3. Profile and place BTB High Street intersection, construct roundabout, lay asphalt, September 2017
  4. Profile and place bitumen treated base (BTB) Church Street – High Street excluding intersections, early October  2-3 days (night works)
  5. Replace garden bed kerbing,  mid to late October
  6. Lay asphalt Church – High Streets, early November
  7. The Church Street intersection and roundabout will be undertaken once service relocations are completed at this intersection.

During 2017/2018 various kerb and footpath replacements will also be undertaken. Council staff will liaise with individual residents and business owners to minimise disruptions.

Further information will be advertised closer to the actual works.